Map your business process before you commission software

TB
ThynkBlox Team
Engineering

To map a business process before software, pick one process and write down what actually happens, not what the manual says. For each step record the trigger, the person, the system used, the information passed on, the exceptions and the waiting time. A plain table is enough. Once it is on paper, you can decide what to fix, what to automate and what to leave alone.

Why map a process before you commission software?

Software copies the way work is done. If the way is unclear, the software will copy the confusion, and you will pay to automate steps that should not exist. A map also gives a developer something concrete to quote against, instead of a loose description such as "we need an order system".

Mapping does not need special notation or tools. A shared document or a whiteboard photo is fine. The value lies in the questions it forces you to ask, and in the fact that the people who do the work see it written down and can correct it.

What should you capture for each step?

Walk through one process from the first event to the final outcome. For every step, capture seven things:

  • Trigger: what starts this step, such as a message, a form or the end of the previous step
  • Step: the action, written as a verb and an object
  • Person: the role that does it, not a name
  • System: where the work happens, such as a spreadsheet, a notebook, email, a chat app or a screen
  • Information passed: what is handed on, and in what form
  • Exceptions: what goes wrong or differs from the normal path
  • Waiting: where the work sits idle and for how long

Waiting is the one people forget. Much of the delay in a process often sits in the gaps between steps, not in the steps.

What does a process map template look like?

Use one row per step. Copy this table into a document and fill it in with the people who do the work.

#TriggerStepPersonSystemInformation passedExceptionsWaiting
1
2
3

Add a title line above the table: the process name, where it starts, where it ends and who owns it. Keep the scope to one process. "Everything we do" is not a process.

How do you map a process as it really happens?

Ask the people who do the work, and ask them to show you rather than describe it. A few habits make the map honest:

  1. Follow one real case. Take a recent order and trace it from start to finish, using the messages and notes that exist.
  2. Interview each role separately. People describe their own step well and the neighbouring steps badly.
  3. Record workarounds. A personal spreadsheet or a sticky note is part of the process, so write it down.
  4. Ask "what if?" for each step: what if the item is out of stock, the address is wrong, the customer changes their mind.
  5. Do not fix anything yet. Mapping and redesign are separate jobs. Judging while you map makes people defensive and the map less accurate.

What does a worked example look like?

The example below is invented and illustrative. It describes a small business that sells made-to-order furniture and delivers it to customers. The process runs from customer order to delivery.

#TriggerStepPersonSystemInformation passedExceptionsWaiting
1Customer message arrivesNote the order detailsSales coordinatorChat app and notebookItems, size, finish, addressCustomer is unsure of the sizeReply may wait until the coordinator is free
2Order notedConfirm price and advance paymentSales coordinatorSpreadsheet and phonePrice, payment statusPrice differs from the last quoteWaits for customer to pay
3Payment receivedRaise a job for the workshopSales coordinatorPrinted slipItem specificationDetails copied wrongly onto the slipSlip waits on the workshop desk
4Slip seenCheck materials and set a ready dateWorkshop supervisorStock notebookReady dateMaterial not in stockWaits for supplier delivery
5Ready date setTell the customer the dateSales coordinatorPhone callReady dateCustomer not reachableCall may be made a day later
6Item finishedInspect and packWorkshop teamNonePass or fail noteFails inspection and goes backItem waits for a delivery slot
7Delivery slot fixedDeliver and collect balanceDelivery driverPaper delivery noteSigned note, balance paidCustomer absent, damage on arrivalSigned note returns to the office days later
8Note returnedClose the orderAccounts clerkSpreadsheetFinal payment, closureNote missing or unclearWaits for the note to arrive

Reading down the table, three patterns stand out. The same order details are written by hand three times (steps 1, 2 and 3). Customers are told dates only by phone, and often late. The closing step depends on paper that travels slowly.

How do you decide what to fix, automate or leave?

Go through each step and each wait, and sort it into one of three groups. Order matters: fix first, automate second.

DecisionUse whenExample from the map
FixThe step is unclear, duplicated or exists only because of an earlier flawWriting order details three times; agree one order record
AutomateThe step is clear, repeated often, follows fixed rules and is slow or error-prone by handTelling the customer the ready date once it is set; collecting the signed delivery note
LeaveThe step is rare, needs human judgement or already works wellInspecting the finished item; handling an unsure customer

Some questions help with the sorting:

  • Would this step still exist if we started fresh? If not, remove it rather than automate it.
  • Does it happen often enough to justify the effort of building it?
  • Are the rules the same each time, or does a person decide?
  • What does a mistake here cost?

Automating a broken step makes the mistake faster. Fixing it first is usually cheaper than any software.

What do you do with the map next?

Turn the "fix" and "automate" rows into a short list of needs, written in the words of the people who will use the system. That list is the starting point for a software requirements document, where each need is described with enough detail for a developer to build and price it.

Then agree how you will know each need is met. Software acceptance criteria examples show how to phrase that. If the process currently lives in a spreadsheet, when to switch from a spreadsheet to custom software helps you judge whether a build is justified yet.

What common mistakes should you avoid?

Mapping the ideal, not the real. A map copied from a procedure document hides the workarounds that software must handle.

Mapping too much at once. Pick one process with a clear start and end. A second process can follow once the first is understood.

Leaving out exceptions. The normal path is easy. Much of the difficulty, and much of the cost, tends to sit in cancellations, corrections and missing details.

Ignoring waiting. If you only record the work, you miss where days are lost.

Letting one person draw the map alone. The map should be checked by each role that appears in it.

Jumping to screens. Deciding what the software looks like before you agree what the process should be tends to lock in old problems.

When does this approach not apply?

A very simple, rarely changing task with one person involved may not need a full map. A few sentences may do. Likewise, if you are buying a ready-made tool for a standard task, you may map only to check that the tool fits, not to design anything. The full seven-column map earns its time when several people, systems or handovers are involved, or when you are about to pay for a custom build.

Frequently asked questions

How detailed should a process map be?

Detailed enough that a new colleague could follow the work and spot where it can go wrong, but no more. If a step needs several sub-steps to explain, split it into rows. If a step is trivial, merge it with its neighbour. Eight to fifteen rows suit most processes.

Who should be in the room when you map a process?

Include one person from each role that touches the process, plus the owner who can decide on changes. Add someone who handles exceptions, since they know the awkward cases best. Keep the group small so people speak freely, and check the finished map with each role again.

Do I need special software to map a process?

No. A document with the template table, a spreadsheet or a whiteboard photo is enough for this purpose. The aim is shared understanding and a clear input for a developer, not a polished diagram. Formal notation can come later if your team finds it useful.

Should I map the current process or the one I want?

Map the current one first, exactly as it happens. Then mark what to fix, automate or leave. Only after that, sketch the improved version. Starting with the wanted process hides the workarounds and exceptions that your software will still have to handle.